Early Learning Facility Updates

To best meet the needs of our youngest students in our early learning programs (preschool, Transition to Kindergarten, and Kindergarten), facility updates are needed at all five of our elementary schools. Updates needed include:

  • Adding dedicated restrooms within Pre-K classrooms where feasible  
  • Additional adjustments to existing restrooms to meet the needs of early learners (lowering sinks, toilets, urinals, etc)
  • Updates to playgrounds to ensure our youngest students have equitable access to play equipment
  • Adding classroom storage to meet program needs


*Estimated cost: $1,287,470

*Cost estimates include projected inflation through 2028, which aligns with the anticipated completion timeline for most of the proposed projects. Actual costs may vary depending on project schedules but will not exceed the total voter-approved maximum of $152,048,846.